Aaron PalmerThe Wyoming Department of Transportation (WYDOT) District 4 team from Sheridan gave a presentation Monday night to the Buffalo Community to outline the scope and schedule for the Buffalo Main Street Project in 2025.
Project Engineer Stephan Charles said work still remains this year in Phase 4A, from mid-November through late December, and will include additional storm sewer utilities, manhole replacements, and several hundred feet of concrete storm pipe replacement on North Creekside Street downtown.
He then described the schedule for 2025.
After a Question and Answer session at the meeting, Charles said any questions or concerns on the project could be directed to him orSenior Public Relations Specialist Laura Dalles.
We have listed their contact information with this story at sheridanmedia.com.