Buffalo Council Updated on City Projects

The Buffalo City Council heard updates on the city’s projects during their last regular meeting.
City Works Director Les Hook gave some details on where the Flatiron Drive reconstruction project currently sits.
The Tisdale Water Main project was scheduled to begin in mid May and to be completed within a couple of weeks.
The Bozeman Water line project was also expected to complete installation of the water main that week, with the contractor coming back in to install water taps along the line.
The project is expected to be completed by the end of June.
Hook also reported some minor issues with the Fetterman Project that the contractor will complete soon.
The new slide at the Municipal Outdoor Pool in Washington Park has been installed.