News
WYDOT to Begin Mill and Overlay Work Near Gillette
The Wyoming Department of Transportation and its contractor, Croell, Inc. will begin a mill and overlay of US 14/16 in the Gillette area between mile markers 96 and 99 the week of May 18, 2026 – weather permitting.
According to information released by WYDOT District 4 Senior Public Relations Specialist Laura Dalles, motorists will encounter flagging operations, lane closures, a reduced speed limit, and a pilot car to direct traffic through the work zone.
Motorists will be traveling on a milled surface which may include loose gravel and are encouraged to keep a safe distance between cars to reduce the chance of windshield damage. The project is scheduled to be completed by June 30, 2026.