WYDOT Presentation Outlines Buffalo Main Street Project in 2025

Avatar photo

Published

on

The Wyoming Department of Transportation (WYDOT) District 4 team from Sheridan gave a presentation Monday night to the Buffalo Community to outline the scope and schedule for the Buffalo Main Street Project in 2025.

WYDOT Senior Public Relations Specialist Laura Dalles said the team would go over what happened in 2024 and what remains to be done in 2025.

She introduced Project Engineer Stephan Charles, who gave more details on what was accomplished this year.

Charles said work still remaining this year will be Phase 4A, which will happen mid-November through late December, and will include additional storm sewer utilities, manhole replacements, and several hundred feet of concrete storm pipe replacement on North Creekside Street downtown.

The remainder of the project is scheduled for 2025, and we will look at that in an upcoming story.