Ron RichterIn mid November the Wyoming Department of Transportation and Oftedal Construction, Inc. completed the first phase of the resurfacing and utilities upgrade project of downtown Main Street. During a recent interview on Sheridan Media’s Public Pulse program, Sheridan Mayor Rich Bridger reflected on phase one of the project.
The project, which began in April, included removing the fifty-plus year old pavement, installing a new water and storm sewer system, upgrading portions of sidewalks to meet ADA requirements, updating traffic signals, and repaving the roadway. Phase two of the project is scheduled to begin in April of 2024 and will include closing Main Street from Loucks Street to the Coffeen Avenue and Brooks Street intersection.