City Projects Stall Due to Weather

Avatar photo

Published

on

Projects in the City of Buffalo have been shut down periodically over the last couple of weeks due to weather condisitions.

According to Project Engineer Brent Bennett with Nelson Engineering, the Flatiron Drive project has seen the most weather-related issues.

Bennett said the contractor will be finishing the storm drain and then start building the roadway back, along with water line work and moving fire hydrants in preparation for widening the road.

Bennett also reported that he contractor is on-site and progressing with the Bozeman Water Line project.