Sheridan Commission OK’s Changes for Sheriff’s Office Remodel

Two Change Orders on the Sheriff’s Office Remodel project have been approved by the Sheridan County Commission.

Change Order#008 includes rerouting of ducts, labor to remove a door opening for relocation, and an additional door that matches the original.

The cost of the change order is just under $5,800.

Change Order #010 consists of furring out a wall and construct a ceiling soffit, adding additional studs, labor, and adding additional cover plates.

According to languageofcarpentry.com, furring is the process of adding extra wood to a structure to give it additional depth.

The cost of the second change order is nearly $2,500.

The two change orders are expected to add two days to the schedule of the overall project.

The commission ratified the change orders during their recent meeting.